Surface Facilities Request for Proposal (RFP)
| Request for Proposal (RFP) | TC Bid Package Review Issue Date |
RFP Issue Date | RFP Response | Target PO Issue |
|---|---|---|---|---|
| Gasification Island | 13-Nov-07 initial | 02-Jan-08 | 27-Feb-08 | 18-May-08 |
| Process Control System | 13-Nov-07 initial | 16-Jan-08 | 21-Feb-08 | 29-Apr-08 |
| Combustion Turbine Gen (CTG) | 24-Jan-08 | 15-Feb-08 | 14-Apr-08 | 14-May-08 |
| Steam Turbine Gen (STG) | 24-Jan-08 | 15-Feb-08 | 25-Apr-08 | 30-May-08 |
| Heat Recovery Steam Gen (HRSG) | 24-Jan-08 | 15-Feb-08 | 14-Apr-08 | 14-May-08 |
| Sour Syngas Processing Sys | 16-May-08 | 06-Jun-08 | 11-Aug-08 | 26-Sep-08 |
| Air Separation Unit (ASU) | 26-May-08 | 18Jun-08 | 10-Aug-08 | 14-Sep-08 |
| CO2 Compressor | 09-Jun-08 | 30-Jun-08 | 24-Aug-08 | 28-Sep-08 |
Contact David Brown at tel: 469-442-7974 for minimum criteria and other important information.