Artist Concept of the FutureGen Power Plant

Solicitations

Last Updated: December 19, 2007

Surface Facilities Request for Proposal (RFP)

Request for Proposal (RFP) TC Bid Package
Review Issue Date
RFP Issue Date RFP Response Target PO Issue
Gasification Island 13-Nov-07 initial 02-Jan-08 27-Feb-08 18-May-08
Process Control System 13-Nov-07 initial 16-Jan-08 21-Feb-08 29-Apr-08
Combustion Turbine Gen (CTG) 24-Jan-08 15-Feb-08 14-Apr-08 14-May-08
Steam Turbine Gen (STG) 24-Jan-08 15-Feb-08 25-Apr-08 30-May-08
Heat Recovery Steam Gen (HRSG) 24-Jan-08 15-Feb-08 14-Apr-08 14-May-08
Sour Syngas Processing Sys 16-May-08 06-Jun-08 11-Aug-08 26-Sep-08
Air Separation Unit (ASU) 26-May-08 18Jun-08 10-Aug-08 14-Sep-08
CO2 Compressor 09-Jun-08 30-Jun-08 24-Aug-08 28-Sep-08

Contact David Brown at tel: 469-442-7974 for minimum criteria and other important information.